The Ontario Science Centre is shutting down immediately as an engineering report commissioned by the province shows the roof could collapse — but while it could be fixed at a cost, the province is choosing to shutter the location indefinitely.
The province announced Friday that a type of lightweight concrete, popular in the 1960s when the building was constructed, has now proven problematic and requires costly repairs.
The abrupt closure comes after the government’s controversial announcement in 2023 that the popular landmark and attraction would be moved to the Ontario Place site — a move it says will save costs.
While the building is safe to enter now, it won’t be by the end of October with the threat of snow, the report notes. As such, the province says it needs to be emptied now.
“The actions taken today will protect the health and safety of visitors and staff,” said Infrastructure Minister Kinga Surma in a news release. “We are making every effort to avoid disruption to the public and help the Ontario Science Centre continue delivering on its mandate.”
You can read the full engineering report at the bottom of this story.
The province’s decision to move the site has received backlash from opposition parties, advocacy groups and the Thorncliffe Park neighbourhood where the science centre is situated — a community with a high population of young children and limited recreational space.
An engineering report this week by Rimkus Consulting Group showed each of the centre’s three buildings contain roof panels in a “distressed, high-risk” condition, the Ministry of Infrastructure said in a news release.
Fixing roof would cost up to $40M: ministry
The panels require fixing by Oct. 31, 2024 to “avoid further stress due to potential snow load which could lead to roof panel failure,” the release said.
Fixing the roof will cost between $22 million and $40 million, the ministry said, requiring the centre be closed for up to two years.
“These estimates are incomplete and subject to change,” said the ministry, noting the costs make up only a “small portion” of the funding needed to keep the science centre open.
The government says the centre needs $478 million to tackle its “failing infrastructure” and sustain programming.
The province is choosing not to implement those fixes. Instead, the science centre will be moved to a temporary location before it ends up at Ontario Place, officials said at an online news conference Friday afternoon.
Lightweight concrete problematic: IO
In the news conference, Infrastructure Ontario (IO) said in was provided with a building analysis from engineering firm Pinchin in 2022 that showed the building was in desperate need of multiple repairs.
“The mechanical issues in the building have continued to worsen,” said Michael Lindsay, IO president.
The lightweight concrete, called reinforced autoclaved aerated concrete (RAAC), featured in the science centre was a popular substance when the science centre was built in the late 1960s. But it is now known that the material can be problematic when exposed to moisture, said Lindsay.
IO has identified 79 provincial buildings with concerns about this concrete, 49 of which are occupied. Those buildings have “enhanced management” to combat issues to due with RAAC, said Lindsay.
“Where we found critical spots … we’ve had appropriate mitigation in-place” for water management with the roof, he said. “But the reality is, is that the roof of the science centre is really at the end of its life.”
The new science centre at Ontario Place is set to open in 2028, said Lindsay.
Michael Robertson, the assistant deputy minister with the Ministry of Infrastructure, said there are no “immediate” job losses for science centre staff. But he couldn’t say if there will be guarantees for job retention in the future.
Robertson said that while the building is safe today, they need four months before the winter to empty out the facility.
Campers to be reimbursed
The science centre runs summer camps that were set to begin in early July. The province says science centre members and summer camp participants will be reimbursed within 30 days, in addition to being offered a free camp location at a nearby school.
The government says Infrastructure Ontario will put out a request for proposals on Monday for a temporary science centre location, before it is moved to Ontario Place.
In the interim, it says the science centre will be looking to host programming virtually or through “pop-up experiences.”
Ford ‘trying to pull a fast one’ with closure: MPP
Floyd Ruskin, the co-chair of advocacy group Save Ontario’s Science Centre, says Premier Doug Ford’s government is focused on constructing a private spa on the Ontario Place site run by the company Therme.
“Doug Ford will proceed to close the science centre … just for the sole purpose to reward Therme spa and Ontario Place,” he said outside of the centre Friday.
“This is a crisis created by the government by not properly funding it,” he said.
Adil Shamji, the Liberal MPP for Don Valley East, spoke alongside Ruskin.
“Of all days that Doug Ford could claim the roof of the science centre is at risk of collapsing, it has to be the same year that he is proposing to move the science centre to Ontario Place … to support a private foreign spa company,” he said.
Shamji said Ford allows public infrastructure to fall apart in order to advance private interests.
“This is Doug Ford trying to pull a fast one,” he said.
Closure ‘heartbreaking’: NDP
“Closing a world-class science and cultural institution is heartbreaking,” provincial NDP Leader Marit Stiles said on X, formerly Twitter.
She said the government’s “real motive” is to justify constructing a spa.
“The [province] could have invested in revitalizing the Science Centre, but instead it’s using our public money to concoct a sham business case against this important community hub,” she said.